The first unit of Rivne NPP was disconnected from the network for repair

Scheduled maintenance of the first unit designed for 45 calendar days. Remain in operation for another three units.

At the Rovno nuclear power plant for scheduled maintenance disconnected the power unit №1, reported the press service of “Energoatom”, reports the Chronicle.info with reference to korrespondent.net.

The unit was turned off yesterday in 10:23 in accordance with the schedule of repairs of existing NPP power units of Ukraine and in accordance with the agreed bid.

“Currently in the work are of three power units of Rivne NPP. The total capacity of the generators is 2 430 MW”, — stated in the message.

Comments on the operation of the main equipment of operating power units and staff there.

Radiation, fire-prevention and ecological state on the NPP and the adjacent territory is not changed and is within the existing norms, informs a press-service.